don_resqcapt19 said:
It is my opinion, that other then the metering equipment and the supports for the service drop, the utility has no business specifying installation requirements on the load side of the service point. The work on the load side of the service point is covered by the NEC.


I completely agree. What's to stop them from "mandating" anything electrical on a property?
 
don_resqcapt19 said:
It is my opinion, that other then the metering equipment and the supports for the service drop, the utility has no business specifying installation requirements on the load side of the service point. The work on the load side of the service point is covered by the NEC.


You don't have to follow any power company requirements at any time.

Of course they are not obligated to hook your work up either. :cool:
 