LarryFine
Master Electrician Electric Contractor Richmond VA
- Location
- Henrico County, VA
- Occupation
- Electrical Contractor
Me again. Situation: commercial building with existing suspended ceiling, 12' up, with bar-joist roof about 8' higher. I expect to use 3/8" all-thread, washers, and nuts, and Mineralac pipe hangers.
We need to run a 2.5" EMT with four 4-0's and a #4, all copper, about 6' up out of existing switchgear, about 80' horizontally above the ceiling, and about 8-10' down into a trough to feed a pair of panels.
The plans originally called for a main-breaker panel and a sub-fed one, but the owner already has two 200a panels, so I figured I'd split the 4-0's in the trough, and feed both panels with the same size.
1.) Is 3/8" all-thread large enough for this run, or would you recommend 1/2"?
2.) Working on a lift, how long ought it take two guys to run the EMT and pull and terminate the wire, including the trough?
3.) I figure on using split-bolts in the trough to feed the two panels. Alternate suggestions, and why?
"As always, if any of your IM team is caught or killed, the secretary will disavow any knowledge ofyour actions."
Danke!
We need to run a 2.5" EMT with four 4-0's and a #4, all copper, about 6' up out of existing switchgear, about 80' horizontally above the ceiling, and about 8-10' down into a trough to feed a pair of panels.
The plans originally called for a main-breaker panel and a sub-fed one, but the owner already has two 200a panels, so I figured I'd split the 4-0's in the trough, and feed both panels with the same size.
1.) Is 3/8" all-thread large enough for this run, or would you recommend 1/2"?
2.) Working on a lift, how long ought it take two guys to run the EMT and pull and terminate the wire, including the trough?
3.) I figure on using split-bolts in the trough to feed the two panels. Alternate suggestions, and why?
"As always, if any of your IM team is caught or killed, the secretary will disavow any knowledge ofyour actions."
Danke!