Have a GE and Siemens supplier who is telling me Gangable meter banks (6 meters) for an apartment complex have a 13 month lead time. Anyone have better luck with a different brand, or is it the same for Square D and Cutler Hammer? Thanks

In NC, but I assume this is basically the same nationally.
 

farmantenna

Senior Member
Location
mass
we were given 265 days 5 months ago for Siemens POWMOD. And to worsen things my boss and supplier ordered wrong ones and I caught it 1.5 month after order. so back of the line we went.
 

farmantenna

Senior Member
Location
mass
we ordered Siemens POWMOD .6 sections for 30 meters and 200 3ph house and main

for 6 total meters why gangable? more than one section? Milbank have 6?
 

kwired

Electron manager
Location
NE Nebraska
Square D was having those sort of problems last year. Sounds like it is sort of cleared up but still likely longer delays than there was 4-5 plus years ago to get some items. Lead times may be just a few weeks now instead of several months.
 

brantmacga

Señor Member
Location
Georgia
Occupation
Former Child
I was told recently that CH gangable meters were down to 6-9/mo lead time.