Have a GE and Siemens supplier who is telling me Gangable meter banks (6 meters) for an apartment complex have a 13 month lead time. Anyone have better luck with a different brand, or is it the same for Square D and Cutler Hammer? Thanks

In NC, but I assume this is basically the same nationally.
 
we were given 265 days 5 months ago for Siemens POWMOD. And to worsen things my boss and supplier ordered wrong ones and I caught it 1.5 month after order. so back of the line we went.
 
we ordered Siemens POWMOD .6 sections for 30 meters and 200 3ph house and main

for 6 total meters why gangable? more than one section? Milbank have 6?
 
Square D was having those sort of problems last year. Sounds like it is sort of cleared up but still likely longer delays than there was 4-5 plus years ago to get some items. Lead times may be just a few weeks now instead of several months.
 
I was told recently that CH gangable meters were down to 6-9/mo lead time.