PVfarmer
Senior Member
- Location
- Newport County, Rhode Island, USA
Let's look at this from the other side and eliminate the situations where we can all agree that batteries as an adjunct to PV are definitely a bad idea, OK? I'll start:
1) For a facility (home or business) where the facility immediately uses all the power the PV system produces, i.e., the meter never "runs backwards".
2) For areas where there is net metering, i.e., the meter runs backwards and forwards and the utility is only concerned with the bottom line at the end of the month - grid storage is free.
The first: why not? When the meter only runs forwards, you can stop it from doing that at night, or for a business in early evening and morning...with a BESS of course.
The second: why would you want the meter to run forward if you could lower that cost with a BESS?
Check this out- the words I've been looking for-
Avoided Cost.
Both a real thing (according to governmental accountants anyway) and a GOOD thing!
measure of what it would cost the grid to generate the electricity = change it to "what it would cost you (the consumer) to pay the POCO to generate the electricity that is otherwise displaced by a new generation project"
New generation project being = to PV system with and without BESS, for accurate comparison.
Since projected utilization rates, the existing resource mix, and capacity values can all vary dramatically across regions where new generation capacity may be needed, the direct comparison of LCOE across technologies is often problematic and can be misleading as a method to assess the economic competitiveness of various generation alternatives. Conceptually, a better assessment of economic competitiveness can be gained through consideration of avoided cost, a measure of what it would cost the grid to generate the electricity that is otherwise displaced by a new generation project, as well as its levelized cost. Avoided cost, which provides a proxy measure for the annual economic value of a candidate project, may be summed over its financial life and converted to a stream of equal annual payments. The avoided cost is divided by average annual output of the project to develop the "levelized" avoided cost of electricity (LACE) for the project.4 The LACE value may then be compared with the LCOE value for the candidate project to provide an indication of whether or not the project's value exceeds its cost. If multiple technologies are available to meet load, comparisons of each project's LACE to its LCOE may be used to determine which project provides the best net economic value. Estimating avoided costs is more complex than estimating levelized costs because it requires information about how the system would have operated without the option under evaluation.
http://www.eia.gov/forecasts/aeo/electricity_generation.cfm#4
When avoided costs = the bill that you didn't pay, it isn't too much more complex...