goldstar
Senior Member
- Location
- New Jersey
- Occupation
- Electrical Contractor
I’m posting this as a point of information so that in the event any of you get yourselves into a situation like I have you’ll know what to do. There’s an unspoken rule that states ANY TIME you get to do electrical work on a commercial job – make sure you have a well written and signed contract.
On November 15, 2017 I began working for a GC wiring what started out as a small amount of electrical work at a renovated tire center (installing a few receptacles and wiring a 3 ton AC unit). At the time the situation didn’t call for a contract and there was no set of plans on which to bid. Well, the job started to grow exponentially and a $5K job grew to a $23.5K job over the course of 3 months (new car lifts, 3 phase air compressor, lighting, etc.). On December 15th I was issued a check for $8K and applied it to the invoices accordingly but continued to do more work through January 2018. On January 11th the GC issued me a check for $15.5K for the balance with the understanding that I would hold the check until the following week when he got paid from the garage owners. Well, next week - led to next week - led to next week until finally it was almost 3 months. I consulted my attorney who advised me to deposit the check.
Within 2 days the check came back NSF. At that point I brought all my documentation to my attorney. He then advised me that bouncing a check for that amount is fraud and we should go after the GC on criminal charges. A day later he came back to me and advised me that he was not able to file criminal charges because that had to be done within 45 days of the date the check was issued.
Now, my next choice is to file a lien on the building (which is being leased by the tire repair company) for the outstanding $15.5K which I have done. It should be noted that in order to do that you would have to file the lien WITHIN 90 DAYS OF THE LAST DAY YOU WORKED ON THE JOB. Luckily, I fit into that time frame.
What does all this mean ? Currently I’m out $15.5 K. The lien will stay attached to the building until the owners decide to sell that building. They will not be able to sell it until the lien is satisfied. That could be next week, next year or 10 years from now.
The long and short of this is – make sure you have a contract. In all fairness you’ll always need to have some trust in the people you work for and that they’ll pay you but, as President Reagan once said “Trust But Verify”. Verify with a contract and get progress payments if you can.
On November 15, 2017 I began working for a GC wiring what started out as a small amount of electrical work at a renovated tire center (installing a few receptacles and wiring a 3 ton AC unit). At the time the situation didn’t call for a contract and there was no set of plans on which to bid. Well, the job started to grow exponentially and a $5K job grew to a $23.5K job over the course of 3 months (new car lifts, 3 phase air compressor, lighting, etc.). On December 15th I was issued a check for $8K and applied it to the invoices accordingly but continued to do more work through January 2018. On January 11th the GC issued me a check for $15.5K for the balance with the understanding that I would hold the check until the following week when he got paid from the garage owners. Well, next week - led to next week - led to next week until finally it was almost 3 months. I consulted my attorney who advised me to deposit the check.
Within 2 days the check came back NSF. At that point I brought all my documentation to my attorney. He then advised me that bouncing a check for that amount is fraud and we should go after the GC on criminal charges. A day later he came back to me and advised me that he was not able to file criminal charges because that had to be done within 45 days of the date the check was issued.
Now, my next choice is to file a lien on the building (which is being leased by the tire repair company) for the outstanding $15.5K which I have done. It should be noted that in order to do that you would have to file the lien WITHIN 90 DAYS OF THE LAST DAY YOU WORKED ON THE JOB. Luckily, I fit into that time frame.
What does all this mean ? Currently I’m out $15.5 K. The lien will stay attached to the building until the owners decide to sell that building. They will not be able to sell it until the lien is satisfied. That could be next week, next year or 10 years from now.
The long and short of this is – make sure you have a contract. In all fairness you’ll always need to have some trust in the people you work for and that they’ll pay you but, as President Reagan once said “Trust But Verify”. Verify with a contract and get progress payments if you can.