We installed several lights on an exposed ceiling room. The fixtures were hung from the ceiling with cables about 3' down. We wired to them with prefabed whips that were 6' long so we put a loop in the whip. The inspector said we weren't allowed to have a 360 degree bend in the whip (greenfield) and had to take out the loop. Is there any validation to that in the NEC?
Sent from my SCH-I435 using Tapatalk
Sent from my SCH-I435 using Tapatalk

is UL Listed under the Wiring Assemblies (QQYZ) category.