Even with a power tugger you are going to need more than the 2x2 guys on that size wire. If you want less guys that the 8 most have said and they would likely being shifted around on the tasks to keep it going with that heavy load, you should plan on a power spooler coupled with the power tugger with a remote. Then you would just have they 4 guys as floaters to chase the snags.
Agree with
@tburdick, estimators should spend some time on these jobs before they give a lowball labor, that the GC and owners will inevitably complain to the EC "Why is it taking so long, the Estimate said only this much?".