klett@abingdon-va.gov
Member
- Location
- Abingdon VA
We just had arc flash labels installed on our MCC's.  Half of the MCC's now have a "Danger" label located at the top of each section.  If the work to be performed is done within a bucket that is installed, shouldn't it have it's own label?  As of right now, I would have to shut down the entire MCC just to replace a control voltage fuse.
A second question is how do you verify that the power is off if there is not a level off PPE that would allow you to open the door to measure voltage?
	
		
			
		
		
	
				
			A second question is how do you verify that the power is off if there is not a level off PPE that would allow you to open the door to measure voltage?
 
				
 
 
		 
 
		 
 
		