Hi everyone I am new to the forum, so if this can be found somewhere I apologize. I couldn't find exactly what I am looking for. I have been asked to upgrade a 200 amp service on a 6 unit dwelling and add a house panel. I walked the job with the AHJ and he seemed fine with the set up I have listed below but I can't find anything concrete that says its a good install. This is the best setup the supply house could get me. There will be 7 disconnects and my understanding is that you cannot have more than 6 on a service. It seemed like the AHJ was fine with the main disconnect being there for the 7 meters. All of the subpanels will be in the basement.I have not done a service of this magnitude before so I want it to go smoothly. Please let me know any and all thoughts. Thank you for all of the insight.