Alwayslearningelec
Senior Member
- Location
- NJ
- Occupation
- Estimator
Ok, I mentioned to the guy that I'm working for that there were 5-6 parallel runs from and to the same location and according to NECA MLU the labor could be discounted. He said not tue the guys in the field won't do it any faster and their slow as it is. First I thought it was a little short sighted and unfair second is I believe there are valid reasons as to why pulling these feeders and running these conduits could be discounted . Isn't setup on reason? Thanks
Last edited: