it wouldve had to have been parallel 1/0sOne RMC is what I would use. Definitely not an LB with 300 kcmil.
it wouldve had to have been parallel 1/0sOne RMC is what I would use. Definitely not an LB with 300 kcmil.
Im not familiar w the code section that tells you how to get the wire in the pipe only afterWill you have a bucket truck to feed conductors from top? If not and doing this as a one man job, this is where I might violate code and assemble the conduit as I install the conductors. I would do the horizontal section first, then add sweeps and last legs. Call me a hack. If I had the bucket truck, a puller and a helper I would pull it in from top and feed from bottom. If no puller then as Larry said pull from bottom and feed from top. I would do one set of conductors so I didn't have to worry about lugs.
I think i posted this photo back in like 2008but i have this ready to stub it out!
View attachment 2553287
Repeat this to yourselfthats my question now, about how to hoist it best
300.18Im not familiar w the code section that tells you how to get the wire in the pipe only after
Ok, all things aside, funny that pretty was my point.they would even pay for that to keep it purdy
How about renting some scaffolding, not like you need to move it multiple times to do this job.all good!
location: only in california =)
so the slope there is 10% and no snorkle will park and raise,
nobody rents a 30' boom,
they do rent a crane, but
so I either have to build a platform with cribbing for the snork
or...
I am thinking to create a hoist anchor point from the roof
and a small platform that gives me 7+ feet to set the 24' ladder on those porches
Then build the riser with the sweep into a threadless compression fitting
Hang the pipe from the hoist and then fit it to the compression fitting down there and the strut on the wall.
The wire can also be raised by the hoist, draping the belly over some webbing
Of course it is good to have two helpers.
I used to do alot of field engineering when i was a kid,
My boss was a civil engineer in the shipyards
we were always building cranes and levers.
So the question is: rigging
the best way to rig the pipe and
rig the wire to be able to hoist it.
My plan is to drill a 1/4 or 3/8 hole thru the rigid coupling , use some removeable threadlocker
and put a bolt in thru the coupling for a handle
Hoist it up by the bolt its only 12 feet or so
After its all secured, then the rigid coupling can be removed
As for the wire, again, hoist in with webbing from about the midpoint and slide it in there with lots of soap
yeah he's going to build a box around itIf owner wants "pretty" the meter center on front of building already took that away, JMO.
...But then thinking of that, you might attach the top vertical run of the conduit onto a temporary section of conduit to make a longer "pole" that would reach up to where you want it. That way you could tip up this "pole" from the ground, strap the upper conduit in place, and then remove the temporary lower section. I think it would be best if the bottom of this pole was placed over a bolt put into a large board, the concrete slab, etc. to keep the pole from slipping out sideways when it's tipped up vertically. Kind of like tipping up a ladder ... I think.
That’s all true but in this case the scaffold would be in front of the riser and poco may not be able to reach with their boom. It was actually my preferred method after the snorkel. The cost was modest. It is still possible.How about renting some scaffolding, not like you need to move it multiple times to do this job.
Recent years everyone thinks a mechanical lift is absolutely necessary for about everything, and they are often convenient. But older fashioned methods still have a use at times.