Looking to get an opinion on something - going to show someone else - so answer honestly....
Underground service, apparently office full of people working - service conduit and meter relocation - live - no disconnect - 4 hours....
What say you? Honestly....
An Estimator put this on a schedule for tomorrow - I'm yet to see it - but if you heard this over the phone what would you say?
(Paralleling a temp feeder to the main to keep the office going - then demo existing - reconnect new - live)
Looking to get an opinion on something - going to show someone else - so answer honestly....
Underground service, apparently office full of people working - service conduit and meter relocation - live - no disconnect - 4 hours....
What say you? Honestly....
An Estimator put this on a schedule for tomorrow - I'm yet to see it - but if you heard this over the phone what would you say?
(Paralleling a temp feeder to the main to keep the office going - then demo existing - reconnect new - live)
I hope you will post pictures of this folly.
A resi panel change usually takes a minimum of 3 hours. The linemen take anywhere from 15 minutes to 30 minutes to reconnect after arriving and inspecting after we are done. So, you are down to 3? hours there. I think someone is blowing smoke up your aft.
Then me thinks . . . it's one thing to disconnect and reconnect something live and another to do it under load.
I've always scheduled all day for a service change, probably never had one take more than 5 hours, but those were resi too. I always wanted to cover my self for the unexpected on a commercial, I would just tell the owner to give everyone the day off or do it on a weekend.
Looking to get an opinion on something - going to show someone else - so answer honestly....
Underground service, apparently office full of people working - service conduit and meter relocation - live - no disconnect - 4 hours....
What say you? Honestly....
An Estimator put this on a schedule for tomorrow - I'm yet to see it - but if you heard this over the phone what would you say?
(Paralleling a temp feeder to the main to keep the office going - then demo existing - reconnect new - live)
Looking to get an opinion on something - going to show someone else - so answer honestly....
Underground service, apparently office full of people working - service conduit and meter relocation - live - no disconnect - 4 hours....
What say you? Honestly....
An Estimator put this on a schedule for tomorrow - I'm yet to see it - but if you heard this over the phone what would you say?
(Paralleling a temp feeder to the main to keep the office going - then demo existing - reconnect new - live)