I appreciate everyone's input, when we put this plan together originally it felt off to run the smaller wire but we couldn't find a reason why we shouldn't, which is why i posted this. We have also for logistical reasons down sized to a 600 amp load center, and moved it adjacent to our switchgear so instead of a 150' run its become a 20' run, and we will make up the distance with our smaller branch circuits. Unfortunately it has almost double our cost in wire