dingokangaroo said:correct. to see it you have to read
Dingdongaroo.....8" of rock and 2" of asphalt doesn't equal:
18" of cover.
12" of cover over 2" of concrete.
4" of cover over 4" of concrete.
You may need to "read" 300.5
steve
dingokangaroo said:correct. to see it you have to read
hillbilly said:Dingdongaroo.....8" of rock and 2" of asphalt doesn't equal:
18" of cover.
12" of cover over 2" of concrete.
4" of cover over 4" of concrete.
You may need to "read" 300.5
steve
Jim W in Tampa said:14 inches of dirt + 8 inches rock+2 inches asphalt=24
LMAOiwire said:God you love to run at the edge.![]()
georgestolz said:LMAO
This is the first I'd seen this thread - Jim does seem to start more of the "edge of the code" threads than anyone else here, doesn't he?
Always makes for a good discussion, though.![]()
Jim W in Tampa said:14 inches of dirt + 8 inches rock+2 inches asphalt=24
wow. and I'm told I need to "read" lolhillbilly said:Dingdongaroo.....8" of rock and 2" of asphalt doesn't equal:
18" of cover.
12" of cover over 2" of concrete.
4" of cover over 4" of concrete.
You may need to "read" 300.5
steve
thats ok. we all make a mistake or two some times.....unless of course your me.........hillbilly said:I guess that I misunderstood.
Where in you original post did you mention 14" of dirt?
steve
77401 said:It does look like Jim is Binge posting. Another few months & he'll pass you in post George.
Should we have an intervention for Jim?
Jim W in Tampa said:Past that if i get credit for my first name i used.Lost it in a mike holt change over and my server at same time.
He speaks the truth!And yes i do ride the edge ,the straight away doesnt need this forum LOL
georgestolz said:
Actually, Jim, you had 4576 posts under your old screen name, so with the 1065 you have on the new one, that brings you to 5641 posts. Right now I have 5713, which means I only just recently passed you.
If I stand on your shoulders I can almost see Bob.
He speaks the truth!
I've learned a lot from the edge.![]()
iwire said:Good to hear Jim.![]()
Jim W in Tampa said:They cant even put the rock in yet till it passes compaction and it cant.Job is basically stoped.2 more months of rain every day.
hardworkingstiff said:Don't be shy about asking for a change order if they decide to take out that 14".
Jim W in Tampa said:That might just very well happen,