So have 2- 4” PVC conduits interior of bldg.. is RGS but only small portion) w/ 3#500 5kv cables in each going from service building gear on 2nd floor to substation #1 on grade. Total point to point footage of run is 300’. So it’s 300’x3 cables x 2 runs= ~ 1800’ of total wire.
I assume the reels would be setup on grade at the substation as you would not get them on 2nd floor of enclosed building. So tugger would be setup on 2nd floor?
How would you setup your crew to do this pull? How many men on each end. Thinking total crew would be about 6 guys.
When I take what we have for labor per thousand for 1/C #500 I get about 140 hours total to pull these 2 sets. So if it was 6 men at 8 hours each that would be 48 hours per day so about 3 days to do the run. Now if the amount of men is different from 6 then obviously the duration of the pull changes.
Any thought on the # of men and how long to do this pull? Thanks.
I assume the reels would be setup on grade at the substation as you would not get them on 2nd floor of enclosed building. So tugger would be setup on 2nd floor?
How would you setup your crew to do this pull? How many men on each end. Thinking total crew would be about 6 guys.
When I take what we have for labor per thousand for 1/C #500 I get about 140 hours total to pull these 2 sets. So if it was 6 men at 8 hours each that would be 48 hours per day so about 3 days to do the run. Now if the amount of men is different from 6 then obviously the duration of the pull changes.
Any thought on the # of men and how long to do this pull? Thanks.