Greetings, I'm new (first post). Can any of you engineer types or field people tell me 1) if it is a violation and 2) if conductors are inherently changed or damaged by pulling them through more than 360 degrees of bends.  I have 4 - 4/0 conductors and 1 - #2 ground in a 2" EMT conduit, approximately 100' long with 7 ninety degree bends. There is a C-condulet after the 4th ninety degree bend, for lubrication and to satisfy code requirements.  Is there any prohibition against pulling these conductors from point-to-point without stopping?  I believe that there is not, however I have nothing with which to back up my opinion.  Any coherent thoughts would be greatly appreciated.
	
		
			
		
		
	
				
			 
				
 
 
		 
 
		 
 
		 
 
		 
 
		