Re: PVC Sch. 40 conduit
I'm not sure about your location but here in KY you have to use schedule 80 anytime you are above ground. The conduit which enters the ground must also be schedule 80. The first full piece of conduit in the ground can then be schedule 40. Regardless of the situation, I recommend using schedule 80. It is much more durable and is less likely to cause you problems in the future.