Engineer note is saying to feed these receptacles via mill work. So they’d require #10’s.
If fed with flex or hard pipe and daisy chaining would there be an issue with box fill and pulling #10’s through the receptacle boxes? They are separate circuits.
Not sure that’ how it should be done.
If fed with flex or hard pipe and daisy chaining would there be an issue with box fill and pulling #10’s through the receptacle boxes? They are separate circuits.