What is code reqiurment on this application.We have a 2000 Amp 3 phase Service with 5-500mcm per phase.My question is this we are installing a 3 phase lighting panel wye with a 200 amp main breaker.What does the code say about tying directly to top of main service instead of MCC bucket for the lighting panel?The reason is this main service is buried already and we want the lighting panel to be on when power is off for lights in building.