Instead of running to pay a lawyer or the court, a phone call is cheaper. The first phone call is the GC and discuss wording for a partial lien that takes effect when the check clears. If that phone call is not fruitful the next calls are to the landlord and tenant. Neither 1 of them want to be tied up with liens. You don't have to fly off half cocked. Just try to work it out calmly with the parties involved before loosing money through the courts.
They call this a conditional lein upon progress payment.
All EC should have the standard lein release forms. There are several for different purposes.
1) Conditional upon progress paymet ( for the payment not yet made)
2) unconditional Release of lein progress payment
3) conditional waiver and release of Final payment
4) un conditional waiver andrelease of final payment