Hi Everyone,
I am new to the forum and am excited to be part of Mike Holt's community. I am having a 20 Mega Watt generator delivered tomorrow and need to clarify my systems grounding.
If the office sub panel has a neutral/ground bond do I install ground rod below the sub panel and terminate at the panel?
Or is it required that the generator have the Neutral/Ground Bond and ground rod be connected and terminated at the generator ground terminal?
I am having a hard time understanding the code requirements of 250.30 "Separately Derived Systems" and article 550.30 "Mobile home distribution systems. Any help is appreciated.
I am new to the forum and am excited to be part of Mike Holt's community. I am having a 20 Mega Watt generator delivered tomorrow and need to clarify my systems grounding.
If the office sub panel has a neutral/ground bond do I install ground rod below the sub panel and terminate at the panel?
Or is it required that the generator have the Neutral/Ground Bond and ground rod be connected and terminated at the generator ground terminal?
I am having a hard time understanding the code requirements of 250.30 "Separately Derived Systems" and article 550.30 "Mobile home distribution systems. Any help is appreciated.