Just a question, why is the pvc beging changed to steel above ground? If it is becuase of concern for physical damage, shouldn't the steel extend to the depth required by Table 300.5? 300.5(D)(1) seems to say so.Originally posted by vanwalker:
can anyone direct me to thread? for a pvc riser 6" above ground to 4'section of steel conduit into bottom of meterbase, for bonding of this short section requirements. hope this makes sense? THANKS GEO