Any of you guys ever been involved with having to give unit prices to GC once you get the job for conduit, wire etc. in the case of change orders?
I'm always concerned as it's tricky because your never sure if it'll be used as an add or delete. If you give them a chunky unit price that's higher than what was carried in the estimate and there is a delete your screwed.