Ok, let's look at a hypothetical situation.
 
I am asked to provide a feeder to a detached shed and I have to cross the house with this feeder to get to the side of the house where the shed is to be built at which point I will have to change wiring methods.
 
I have scrap NM in the warehouse that will make it from the panel to a location where I will make a splice to UF which is also scrap I have in the warehouse and it is long enough to make it to the shed.
 
I have no problem using these scrap pieces, but I am led to believe there are some here that would buy new rolls of each type of cable for this project, is that correct? :roll:
 
Roger
	
		
			
		
		
	
				
			I am asked to provide a feeder to a detached shed and I have to cross the house with this feeder to get to the side of the house where the shed is to be built at which point I will have to change wiring methods.
I have scrap NM in the warehouse that will make it from the panel to a location where I will make a splice to UF which is also scrap I have in the warehouse and it is long enough to make it to the shed.
I have no problem using these scrap pieces, but I am led to believe there are some here that would buy new rolls of each type of cable for this project, is that correct? :roll:
Roger
 
				
 
 
		 
 
		 
 
		 
 
		 
 
		 
 
		 
 
		 
 
		