Working clearance for 13.8-480V power Transformers

Thermal scans of connections while under load would have to be done while energized.
Agreed. I like viewing windows personally. If it's an issue they are easily added. Post 13-16.
Post 13 specifically. You don’t do that work mentioned in 13 energized.
 
Inevitably there is some idiot out there who will open the transformer while energized for routine examination.
It is all but impossible to idiot proof an installation.

What if the working clearance problem is solved, but some unqualified person opens any energized compartment, much less an MV one, anyway?
 
It is all but impossible to idiot proof an installation.

What if the working clearance problem is solved, but some unqualified person opens any energized compartment, much less an MV one, anyway?

True. But, If there’s an injury or death, how will a jury view it if they can prove a NEC violation was involved?


Sent from my iPhone using Tapatalk
 
True. But, If there’s an injury or death, how will a jury view it if they can prove a NEC violation was involved?


Sent from my iPhone using Tapatalk
What NEC violation?
I said required working clearances are obtained with access gates/doors opened.
Or
Viewing windows could be used so no clearance is required as there are no exposed energized parts.

As the engineer of record, I would have no control if someone willing violates either of these conditions.
And yes I understand everyone gets sued, hoping someone has deep.pockets.
 