tonype
Senior Member
- Location
- New Jersey
1. Photos show damaged SEC conduit (duct tape, service head), yet had AHJ 2009 approval. Should this have been flagged (or does the POCO have say in the matter)?
http://i15.photobucket.com/albums/a352/TonyPE/DSCN3921.jpg
http://i15.photobucket.com/albums/a352/TonyPE/DSCN3920_edited-1.jpg
2. What would generally cause terminal bar connections to fry?
http://i15.photobucket.com/albums/a352/TonyPE/DSCN4026.jpg
3. 200-amp main for 4 family. After the main, there are 5 separately metered systems (each apartment and owner). One apartment panel contains 7 disconnects, though no dedicated main. Is the 200-amp main considered the required main or is a dedicated one needed for this panel.
http://i15.photobucket.com/albums/a352/TonyPE/DSCN3921.jpg
http://i15.photobucket.com/albums/a352/TonyPE/DSCN3920_edited-1.jpg
2. What would generally cause terminal bar connections to fry?
http://i15.photobucket.com/albums/a352/TonyPE/DSCN4026.jpg
3. 200-amp main for 4 family. After the main, there are 5 separately metered systems (each apartment and owner). One apartment panel contains 7 disconnects, though no dedicated main. Is the 200-amp main considered the required main or is a dedicated one needed for this panel.