We all know the 360 Code limit on conduit bends. Jobs I design carefully consider this requirement.
Reviewed some plans that are showing 5 or more 90 degree bends. The pipe is 4" PVC. The bends are RGS. The designer said "the conduit is oversized".
What are your experiences pulling wire in conduit systems with greater than 360 bends?
Reviewed some plans that are showing 5 or more 90 degree bends. The pipe is 4" PVC. The bends are RGS. The designer said "the conduit is oversized".
What are your experiences pulling wire in conduit systems with greater than 360 bends?