Post Roughing Inspection Flag

W@ttson

Senior Member
Location
USA
Hello,

I was wondering what the general consensus is on what happens if something is found by the electrical inspector after the roughing inspection?

Suppose an inspector comes for roughing and passes it. However, he missed something big. Construction continues, drywall goes up. Time for final inspection. Suppose then at the final inspection the same inspector or even a different inspector finds something and flags the install. Now that the walls are up it is very costly to rectify, can the inspector/town be held liable for the costs? Does the Contractor just eat the costs?

What actually happens in this situation?
 

d0nut

Senior Member
Location
Omaha, NE
The contractor is responsible for providing a code compliant installation. If there are contract documents, the contractor is responsible for providing an installation per the plans and specifications. It shouldn't matter when the deviation was discovered. The contractor's responsibility didn't change.
 

acin

Senior Member
Location
pacific grove california
Occupation
general building contractor est.1984 . C 10 elec. lic.as of 8 / 7/ 2020
The contractor is responsible for providing a code compliant installation. If there are contract documents, the contractor is responsible for providing an installation per the plans and specifications. It shouldn't matter when the deviation was discovered. The contractor's responsibility didn't change.
I agree 100 %
 
Top