Every utility company that I have done business with has defined their jurisdiction as up to the point of the meter panel, and anything after that panel would be the local building departments jurisdiction... except for one: LADWP (Los Angeles District of Water and Power). They are not very open with their requirements, and there is no mention in their ESR manual. They like to heavily imply that their jurisdiction is up to the point of the service disconnect.
Does anyone have any experience with this issue in LADWP or any other utility for that matter?