As the subject states. Has this always been there, or was it added to ensure that people understood the impact of rooftop conduits? If it is a "newer" requirement, what were the restrictions before? I wonder because a contractor is asking us to remove and replace conduits for a reroof, at a location where I assume the Electrical Engineers were fairly diligent since about 1995. I feel that if we touch them though, any violation of this code will need to be accounted for. That calculates out to an adjustment factor of a whopping .58 :jawdrop: