Strathead
Senior Member
- Location
 - Ocala, Florida, USA
 
- Occupation
 - Electrician/Estimator/Project Manager/Superintendent
 
As the subject states.  Has this always been there, or was it added to ensure that people understood the impact of rooftop conduits?  If it is a "newer" requirement, what were the restrictions before?  I wonder because a contractor is asking us to remove and replace conduits for a reroof, at a location where I assume the Electrical Engineers were fairly diligent since about 1995.  I feel that if we touch them though, any violation of this code will need to be accounted for.  That calculates out to an adjustment factor of a  whopping .58 :jawdrop:
	
		
			
		
		
	
				
			
				