J. Hofstetter
Member
- Location
- Berne, Indiana, USA
Is it acceptable to make the connection to the Ufer outside of the concrete? Due to incoming weather, the concrete contractor is speeding up his timeline and I can't be onsite to cadweld the GEC to the rebar before the concrete is poured so the contractor said that he will stub rebar out under his form and I can connect to that. I've never done it this way before and I can't find anything that says I can't, but I'm just not sure. Any help with this is appreciated.