I hate relying on reps for switchboard layouts

binwork91

Senior Member
Location
new york
Occupation
electrical engineer
Lead times for electrical equipment, especially for MV and LV swgr have become the critical path in most projects. We have found using OEM's is the best bet to decrease the lead time. We buy our equipment direct, no reps, and even that doesn't make much difference; generally speaking.
Some contractors I know, they prefer not to order switchboards due to long lead times; instead, they opt for disconnect switches.
 
Top