kwired
Electron manager
- Location
- NE Nebraska
- Occupation
- EC
Not the same situation as the OP has, there are countertops and finished product does not meet code. OP has finished product - that is subject to being changed one day. Would you rather see them place outlets near the floor and when cabinets are added cover them up? The installed outlets in OP comply with 210.52(4), if someone installs cabinets later who says they will be same layout on original plan and some spacing violations don't come up at that time. What if they choose to just place carts or tables against the wall instead of permanent counters?I know plenty of times one of my inspectors approved countertop receptacles only to find that counters were changed on final (shifted) only to end up not being within 2' of the sink...more like 2 1/2' then wanted to cry the blues...code says 2'... not my problem but they would still call and complain to city and go so far as say the inspector approved it at rough in...wrong. If the counter is in (cost spent) then less chance for change. Just trying to give you the inspectors view.
Like I said before if in a situation where plans have to be submitted and you must install to them - then you need to have an approved plan change to omit the counters, but outside of that whatever is there at final is what inspection needs to based on.
If building official doesn't like there not being any counters then he is the one that needs to fail inspection because they are not there, not the EI. If EI wants to approve pending the building official approving the missing counters - then I don't have as much issue with that approach.Also I know things are a bit lax out in Colorado with all that legal "POT" smokin and all....but in most states Inspectors have rules they must follow as "technical assistants" to the building official. If this OP would like to take their case to the Building Official then I suggest they choose that option. Otherwise, put the counters in, get the inspection and move to the next job.
Maybe I was just a Cold Heartless Contractor before moving to the municipal world....but when I did a job I got paid or liens are filed. But that's a totally different topic for another time.